Hi,
intrigeri wrote (08 Dec 2013 17:19:51 GMT) :
>   2014-01-18   package new Firefox ESR
>   2014-01-18   build and upload final ISO
>   2014-01-19   test final ISO
>   2014-01-20   test final ISO
>   2014-01-21   release
I've messed up. Since I've sent this email, Mozilla postponed all
future releases a bit: 
https://wiki.mozilla.org/RapidRelease/Calendar
So, the schedule for the next steps towards 0.22.1 becomes:
  2014-02-01   package new Firefox ESR
  2014-02-02   build and upload final ISO
  2014-02-03   test final ISO
  2014-02-04   release
Can anyone else than me take over the Release Manager role for these
last steps? Worst case, I can do it, or part of it, but it's quite
painful for me.
Core developers: ASAP, please volunteer for the test days, or make it
clear that you can't make it, so we can reschedule slightly if needed.
Thanks in advance!
Note that this *also* postpones 0.23, 1.0 and 1.1. See our updated
release calendar: 
https://tails.boum.org/contribute/calendar/
Cheers,
-- 
  intrigeri
  | GnuPG key @ https://gaffer.ptitcanardnoir.org/intrigeri/intrigeri.asc
  | OTR fingerprint @ https://gaffer.ptitcanardnoir.org/intrigeri/otr.asc